05.05.2020

Nizhnevartovsk thermal power plant on the map. Energy without limits


The power plant in the village of Izluchinsk, Nizhnevartovsk District, Khanty-Mansi Autonomous Okrug-Yugra is one of the main suppliers of electricity throughout the Urals Federal District. This is the last power plant in Russia, the construction of which began in the 21st century and was completed in the 21st.

The design of the new turbine at Nizhnevartovskaya GRES is unique: it operates using the latest efficient combined cycle technology.

The first power unit was put into operation in 1993. The second is in 2003. The third power unit was commissioned in 2014.

Installed electric power of the station 1600 MW, installed thermal power: 758 Gcal/hour. The main type of fuel is natural gas.

Data

After the launch of the first block in 1993 further development stopped, and power unit No. 2, the construction of which had already begun, turned into a long-term construction. The reason for this was the unstable situation in the country. The situation changed in early 2000, when construction resumed as part of the investment program of the Russian Energy System.

The shares of ZAO Nizhnevartovskaya GRES are owned by NVGRES HOLDING LIMITED (NHL). IN authorized capital NHL 75% minus 1 share is owned by JSC INTER RAO - Electric Power Generation, and 25% plus 1 share became owned by JSC NK Rosneft after the latter bought TNK-BP.

The settlement of Izluchinsk did not exist until 1988. It arose exclusively in connection with the construction of the state district power station. The name of the village comes from its location - in the bend of the Vakh River. Today Izluchinsk is the largest and most comfortable settlement in the Nizhnevartovsk region.

Today, the General Director of the Nizhnevartovskaya GRES is Alexander Petrovich Pashchenko. He has been working at energy enterprises since 1979. It has been working for the benefit of Nizhnevartovskaya GRES since its very foundation. Since 2002, Pashchenko has worked as a Deputy Chief Engineer for the operation of the State District Power Plant, and since 2003, as a Chief Engineer. In 2005, Pashchenko was appointed director of the State District Power Plant. In the summer of 2011, Pashchenko was elected head of the Nizhnevartovsk region and chairman of the district Duma.

JSC Inter RAO – Electric Power Generation combines almost all Russian generating assets of the Inter RAO Group, with the exception of power plants in the Omsk and Tomsk regions and Bashkiria. Today, the company includes 17 largest power plants with a total capacity of 22,578 MW.

Among all the GRESs owned by Inter RAO, Nizhnevartovskaya is fifth in terms of installed electric capacity of 1,600 MW (Kostromskaya GRES is the leader with a record 3,600 MW), and in terms of installed thermal capacity of 758 Gcal/h, it ranks first.

Location: Khanty-Mansiysk Autonomous Okrug - Yugra, Nizhnevartovsky district, settlement Izluchinsk
Installed electric capacity of the station: 2,031 MW
Installed heat output: 758 Gcal/h
Main and reserve fuel: associated gas of the Belozerny and Nizhnevartovsk gas processing plants
Emergency fuel for the heating and starting boiler house: fuel oil
Commissioning - January 30, 1993


Year of birth: 1962

Education:

Tomsk Order of the October Revolution and the Order of the Red Banner of Labor Polytechnic Institute. CM. Kirov (Tomsk)

Professional experience:

August 2019 - present - Director of Nizhnevartovskaya GRES JSC.

2018 - 2019 - Director of the Branch "Urengoyskaya GRES" of JSC "Inter RAO - Electric Power Plants".

2018 - Deputy technical director Chelyabinsk State District Power Plant (CHPP-4) PJSC Fortum.

2015 - 2016 - Deputy Technical Director for the operation of the Order of Lenin of the Chelyabinsk State District Power Plant of the branch "Energy System "Ural" of OJSC "Fortum".

2013 - 2015 - Deputy chief engineer for operation of the Nyaganskaya GRES branch of OAO Fortum.

2011 - 2013 - Senior shift supervisor of the power plant of the branch "Nyaganskaya GRES" PJSC "Fortum".

1998 - 1999 - senior shift supervisor of the power plant Tomsk CHPP-3 "Tomskenergo".

1990 - 1998 - shift supervisor of the power plant Tomsk CHP-3 "Tomskenergo".

1988 - 1990 - shift supervisor of the electrical shop of the power plant Tomsk CHPP-3 "Tomskenergo".

1984 - 1987 - Worked his way up from a worker to a shift supervisor of the electrical shop of the Tyumenskaya CHPP-2 Tyumenenergo power plant.

Awards:

2013 - Gratitude of the Governor of KhMAO.

2014 - Gratitude of the branch "Nyaganskaya GRES" JSC "Fortum".

2016 - Gratitude of the branch "Chelyabinsk State District Power Plant" (CHP-4) PJSC "Fortum".

Nizhnevartovskaya GRES is one of the main suppliers of electricity to the Urals Federal District. It was built primarily for the needs of oil and gas companies located in the largest region of the Khanty-Mansiysk Autonomous Okrug - Yugra. In addition, the station supplies electricity and heat to the residents and enterprises of the village of Izluchinsk. Nizhnevartovskaya GRES is considered one of the most environmentally friendly power plants, its technological processes have a high degree of automation.

After the launch of the first power unit in 1993, the construction of the GRES was mothballed and resumed in 2000 as part of the investment program of the Russian Energy System. October 13, 2003 introduced into commercial operation power unit No. 2.

In 2014, power unit No. 3 with an installed capacity of 413 MW was put into operation. The new power unit has a unique combined cycle equipment that meets the most stringent modern standards environmental safety and energy efficiency.

The shares of JSC Nizhnevartovskaya GRES are owned by JSC Inter RAO - Electric Power Plants and the company group PAO NK Rosneft.

---------------

Khanty-Mansi Autonomous Okrug - Yugra belongs to the Ural Federal District. According to the charter of the Tyumen region, Yugra is part of the Tyumen region, but at the same time it is an equal subject Russian Federation. The administrative center of Yugra is the city of Khanty-Mansiysk. The Khanty-Mansiysk Autonomous Okrug occupies a leading position in the subjects of the Russian Federation in terms of industrial production, electricity production, oil and gas production, the volume of investments in fixed capital and the receipt of taxes in the budget system. On this moment more than 10 billion tons of oil have been produced in Yugra since the beginning of the development of the oil and gas province Western Siberia. The Khanty-Mansiysk Autonomous Okrug produces about 7% of world oil and more than half of Russian oil.

Location: Khanty-Mansiysk Autonomous Okrug - Yugra, Nizhnevartovsky district, settlement Izluchinsk
Installed electric capacity of the station: 2,013 MW
Installed heat output: 758 Gcal/h
Main and reserve fuel: associated gas of the Belozerny and Nizhnevartovsk gas processing plants
Emergency fuel for the heating and starting boiler house: fuel oil
Commissioning - January 30, 1993

Nizhnevartovskaya GRES is one of the main suppliers of electricity to the Urals Federal District. It was built primarily for the needs of oil and gas companies located in the largest region of the Khanty-Mansiysk Autonomous Okrug - Yugra. In addition, the station supplies electricity and heat to the residents and enterprises of the village of Izluchinsk. Nizhnevartovskaya GRES is considered one of the most environmentally friendly power plants, its technological processes are highly automated.

After the launch of the first power unit in 1993, the construction of the GRES was mothballed and resumed in 2000 as part of the investment program of the Russian Energy System. On October 13, 2003, power unit No. 2 was put into commercial operation.

In 2014, power unit No. 3 with an installed capacity of 413 MW was put into operation. The new power unit has unique combined cycle equipment that meets the latest environmental safety and energy efficiency standards.

The shares of ZAO Nizhnevartovskaya GRES are owned by NVGRES HOLDING LIMITED (NHL). 75% minus 1 share in the authorized capital of NHL belongs to JSC Inter RAO - Electric Power Plants, and 25% plus 1 share belongs to JSC NK Rosneft.

**************************************** ************
Nizhnevartovskaya GRES is a thermal power plant (GRES) located in the working settlement of Izluchinsk, Nizhnevartovsk District, Khanty-Mansi Autonomous Okrug, 15 km from the city of Nizhnevartovsk, on the banks of the Vakh River. Belongs to ZAO Nizhnevartovskaya GRES - joint venture OAO OGK-1 and OAO Rosneft. The plant's installed electric capacity at the end of 2010 is 1,600 MW; it includes two steam power units of 800 MW each. Thermal power of the station - 758 Gcal/hour.

The first power unit was put into operation on January 30, 1993. Further construction was mothballed until 2000, resuming as part of the investment program of the Russian energy system.

The second power unit was launched on November 14, 2003. The construction work was carried out by OJSC Energostroyinvest-Holding.

In 2014, power unit No. 3 with an installed capacity of 413 MW was put into operation.

**************************************** *************

Nizhnevartovskaya GRES is a power plant located in the working settlement of Izluchinsk, Nizhnevartovsk District, Khanty-Mansi Autonomous Okrug, at a distance of 15 km from the city of Nizhnevartovsk, on the banks of the Vakh River.

Currently, CJSC Nizhnevartovskaya GRES is owned by NVGRES HOLDING LIMITED (NHL), a joint venture between energy companies OAO OGK-1 (75% minus 1 share) and TNK-BP (25% plus 1 share).

As of the beginning of December 2013, the plant's installed electric capacity was 1.6 GW (2 steam power units, 800 MW each), and the heating capacity was 758 Gcal/h.

The average annual power generation of the Nizhnevartovskaya GRES is 12.5 billion kWh, heat supply is 220 thousand gigacalories.

As for the efficiency of the youngest and, perhaps, the most environmentally friendly power plant in Europe, its specific consumption equivalent fuel for electricity supply is 302.7 grams per kWh, for heat energy supply - 168.7 kg/Gcal.

The first of two 800-megawatt power units was put into commercial operation on January 30, 1993. Then the construction of the station was mothballed until 2000, in which it was resumed as part of the investment program of the Russian energy system.

Currently, the station is working on the installation of two power units with an electric capacity of 410 MW each, the commissioning of which should be carried out before the end of 2015.

Electrical power: 2,013 MW
Thermal power: 758 Gcal/h
Annual electricity generation: 11,908 million kWh
Year of commissioning: 1993
Main fuel: gas
Auxiliary fuel: gas
Condition: in use

Closed Joint-Stock Company Nizhnevartovskaya District Power Plant (abbreviated name - CJSC Nizhnevartovskaya GRES) is a regional-scale power plant, which is one of the key electricity suppliers in the Urals.

The GRES is located on the territory of the urban-type settlement of Izluchinsk, Nizhnevartovsk District, Khanty-Mansi Autonomous Okrug - Yugra, which is on the very bank of the Vakh River, 15 km from the regional administrative center. Nizhnevartovskaya GRES is owned by a jointly established company (co-founders: OAO Wholesale Generating Company No. 1 and Tyumenskaya national company- VR). IN organizational structure Society includes 23 departments.

History of development

After the power unit No. 1 was launched in 1993, the construction of the GRES was suspended. Contract work was restored only after 7 years - in 2000 as part of the implementation of the investment program of the federal energy system of Russia. On November 14, 2003, power unit No. 2 was launched. In autumn 2006, Nizhnevartovskaya GRES was merged with OAO OGK No. 1 as structural branch. In December 2007, by the Decree of the governing body of OGK No. 1, CJSC Nizhnevartovskaya GRES was legalized, to the balance of which two functioning power units of the GRES were transferred (included in the authorized capital).

Production figures

The installed electric capacity of the GRES (as of the end of 2010) was about 1,600 MW. To generate energy, two steam-powered power units of 800 MW each were installed. The thermal performance of the power plant is 758 Gcal/hour. GRES operates on natural gas, in 2010, the supply of the necessary energy raw materials was carried out through the acquisition from OAO TNK BP Holding.

In 2012 it was produced electrical energy– 12,477 mln kWh, which is 0.01% more than in 2011 and 10% more than in 2010. Reference fuel is consumed for power generation – 302.7 g/kWh. Heat output - 220.1 thousand Gcal. The production of a unit of thermal energy consumes 168.7 kg/Gcal of equivalent fuel.

The launch of the first power unit took place at the beginning of 1993, and the second - a decade later.

Investment plans

In accordance with the terms of the Contract on Joint Investment Activities, JSC OGK-1 is responsible for the construction of the third power unit in two stages. First, power unit No. 3.1 (410-450 MW) will be put into operation with a completion date before the end of 2013. Completion of the second stage of construction with the launch of power unit No. 3.2 (410 MW) is expected by 2016. The fuel for the new blocks will be associated gas produced in the region from TNK-BP's fields.

In 2010, the supplier of the main equipment was agreed - the General Electric company, and also the main designer - OJSC Institute TEP. In 2011, the general contractor was determined - JSC VO Technopromexport. Investment injections into the implementation this project will amount to 40.46 billion rubles.

Capital structure and management

The entire 100% stake in CJSC Nizhnevartovskaya GRES is owned by NVGRES HOLDING LTD (NHL). While 75% (minus one share) in the authorized capital of the NHL belongs to OGK-1, 25% plus one share (blocking stake) is owned by TNK-BP. Both enterprises are jointly implementing an investment project for the construction of a power unit No. 3 of the station based on two CCGT-450 MW.

Head, General Director - Larioshkin Victor Anatolyevich.

In fact, I'm in a bit of a panic right now, because I have absolutely no idea what to write about. This is not the first state district power plant that I shoot for Inter RAO, and my imagination has run out a bit. But, sitting again in the waiting room of Sheremetyevo, before flying to Tyumen, you can think of something. Fortunately, airplanes and the airport set up a pleasant mood and flow of thoughts.

And the steam turbine of the new power unit launched this year, which you see in the first photo, reminded me very much of some kind of hyperdrive spaceship. :)

1. First, a traditional review of the old part. Well, like old. This station is just over 20 years old.

2. The first power unit was launched on January 30, 1993. Despite the collapsed Union and the complete collapse of the economy, funds were found not to abandon the almost finished power unit and not turn it into a great unfinished building. In the photo, the station shift supervisor (or, as it is still customary to informally call people in this position, “station night director”) Igor Burmatov, nearby (in overalls) is Evgeny Kuligin, the shift supervisor of the electrical workshop, the winner in the nomination “Best in Profession” at the All-Russian competition of operational personnel of TPP with CCGT - 2013.

3. Alas, such a fate befell the second block, the construction of which was mothballed until 2000. And only within the framework of the investment program for the reconstruction of the Russian energy system, the work was continued and the unit gave current to the unified energy system on November 14, 2003. By some mystical coincidence, between all three inclusions in the network of NV GRES power units, the difference is exactly 10 years: 1993 - 2003 - 2013.

4. Now it is one of the most modern power plant in Russia. Its capacity, taking into account the third power unit launched this year, is 2,013 MW.

5. Heavy camera work. Also a girl with a camera.

6. At this station, the main and reserve fuel is associated gas from the Belozerny and Nizhnevartovsk gas processing plants.

7. The station was built primarily for the needs of oil and gas companies located in the Khanty-Mansiysk Autonomous Okrug. In addition, the station supplies electricity and heat to the residents and enterprises of the village of Izluchinsk.

8. It is considered one of the most environmentally friendly power plants, its technological processes are highly automated.

9. Steam pipelines from the boiler to the steam turbine. The pressure in the pipe is 250 kg/cm2. The temperature is 545 degrees.

10. Visual control of the oil system of the generator.

11. The first two units have the same capacity - 800 MW.

12. As I have already said, the station is characterized by a high degree of automation and control. From one installation, more than 2000 different parameters are entered into the system.

13. This is a backup control panel.

14. Power unit engineer Alexei Tsoi, representative of the Tsoi dynasty at the Nizhnevartovsk State District Power Plant. The winner of the "Best in Profession - 2014" contest, as well as his brother, Dmitry Tsoi, an electrician of dispatching equipment and teleautomatics.

16. The shareholders of Nizhnevartovskaya GRES are Inter RAO and Rosneft.

17. Feeding turbopump of power unit No. 2.

19. Steam pipeline suspension system.

20. Visual control of deviation of the steam pipeline.

21. Blower fan of power unit No. 2.

23. And now let's go to the new block. generator outputs.

24. Steam turbine and its generator of a new power unit.

25. gas turbine. The total capacity of the new CCGT is 413 MW

26. Some atypical (for me at least) views combined cycle plant. it's actually a chimney.

27. I told you it looks like a hyperdrive!

28. Block control panel of the new power unit.

30. At the press conference :)

31. Thanks a lot press service and all employees of the Nizhnevartovskaya GRES for hospitality and a wonderful tour of the station.


2023
newmagazineroom.ru - Accounting statements. UNVD. Salary and personnel. Currency operations. Payment of taxes. VAT. Insurance premiums